BC 2014: Construction Principles I

Meeting Action Plan 1

 

Communication and Action Plan

Meeting Type

Project 2 Kickoff Meeting

Attendees

Sean, Wei, Alex (F), Dan, Tom (R)

Purpose

To analyze the project and create a schedule

Objectives

Create a work breakdown structure

Create a RACI Matrix

Create a schedule

Agenda Item #1

Go over the project checklist

Options/Points Raised

There is a lot of work to do and a sense of urgency in a short period of time but work is split equally among all participants without worry.

Reliance on each other’s task is key and completing all tasks by dateline.

Decisions/Recommendations

Set up a detailed schedule that the team must abide by

Agenda Item #2

Create a work breakdown structure

Options/Points Raised

Cooperation and work integration is necessary. Relay of information must not be linear. Instead, collaboration on the Powerpoint ppt and webpages as well as all info is crucial.

Decisions/Recommendations

Constant communication to team members through email must be utilized if someone needs help or information.

A second and third team meeting were put on the schedule to allow for integration.

Agenda Item #3

From the work breakdown structure create a RACI Matrix

Options/Points Raised

Work must be split up fairly.

Decisions/Recommendations

Work was split up fairly in order for teammates to be able to complete their given work in the time allotted.

Agenda Item #4

From the RACI Matrix create a schedule

Options/Points Raised

None

Decisions/Recommendations

None

Action Items

Task to be Done

Responsible Party

Due Date

Meeting 1 Documentation

Wei

11/11/07

Information Gathering for Given Section

All

11/11/07

Formalize WBS, RACI and Schedule

Wei

11/16/07



Back to Plumbing Vent Systems Economic Performance- Documentation

 