| Lessons Learned |
|
|
| Project: |
#1 Team Charter |
Date: |
Nov. 15/07 |
| Team: |
#14 |
Members: |
Keith, Cosco, Caleb, Michael, and Javier |
| Subtask |
What Worked |
What Didn't Work |
Ways to Improve |
| Team Wiki Page |
Team collaborated on creating final wiki page |
Each person creating their own format different from
everyone else |
Closer communication to one another |
| Team Documentation |
Taking precise notes at meetings and noting team
progress |
|
|
| Team Charter |
Team brainstormed and agreed on all issues |
|
|
| Team Capabilities |
Team collaborated on Power Point |
Difficulties in finding precise wording for ideas |
|
| Team Analysis |
Talking openly about what each member thought went
well and what didn't work well |
|
|
| |
|
|
|
| Target Analysis: How well did the project/team do... |
| In achieving
goals and meeting project objectives? |
| This was done
effectively as most of the work was done as a group and at the team meetings
allowing problems to be headed off before they arose. |
| At meeting
deadlines and the final completion date? |
| The only issues
here was getting some last minute graphs and such to upload onto the wiki. |
| Were all the
allocated resources appropriate, sufficient, and efficiently used? |
| The team work well
together! |
| What are the key
lessons that can be applied to future projects? |
| 1) A more detailed
and structured schedule for the project |
| 3) Cut down wasted
time spent at meetings |